Hudson River Dredging
Project
The IDR proposes a schedule for Phase 1 of dredging
from May 2007 to the end of October, 2007, six days a week, 24
hours a day. The seventh day would be for equipment maintenance
and repair. Within Phase 1, there would be at least one month
of dredging at the full rate anticipated for Phase 2. This would
serve to test that all systems are able to handle that level of
dredging.
The dredging is proposed to occur in five-acre increments. Once
a five-acre area has been
completed, 40 samples would be taken within that area to determine
whether it is meeting the residuals of less than one ppm. If not,
that area will be re-dredged and re-tested to see if the PCB level
can be reduced to the <1ppm level. If the <1ppm level cannot
be attained, there may be capping or backfilling of clean material
instead of additional dredging in the same location.
There may be up to seven mechanical dredges in total. Mechanical
dredging is especially good for areas with significant debris
on the river bottom, as in the area under consideration. There
may be a need at some point for some small hydraulic dredges in
shallow places in the Hudson, but this isn’t expected to
be necessary most of the time.
The mechanical dredges that are proposed to be used are controlled
by GPS and laser, so the depth and location of dredging will be
extremely precise. The Phase 1 Dredge Area Delineation report
was describes in detail the areas targeted for Phase 1 Dredging.
Up to 12 barges are proposed to be in operation; one tugboat or
fewer per barge will also be used. 134,000-186,000 cubic yards
of backfill may be needed during Phase 1. The habitat restoration
section of the IDR addresses what would be used to replace habitat
where needed. Any water used in the facility or that might have
come into contact with PCBs will go through a water treatment
process before being released into the river. There will be one
fully loaded 81-car train approximately every other day (4 per
week) leaving the facility. There is a need to maintain through-boating
for recreational boats. The Canal Corporation, GEand EPA are discussing
that as an important issue, but have not yet determined how they
will manage this. The inference that through-traffic could be
shut down could be as damaging as the reality in terms of deterring
recreational boats from choosing to go through this area.
The monitoring plan is still being developed. It will describe
the many types of monitoring that will be implemented. Preliminary
noise and light analysis schematics have been included in the
IDR.
In Phase 1, it is expected that 390,000 tons of processed material
will be transported off-site. The purpose of Phase 1 is to determine
the effectiveness of the remediation steps (for example: will
they meet all requirements?), and to provide project mangers a
period in which to make systems adjustments as necessary prior
to Phase 2.
From Hudson River PCBs
Superfund Site Community Advisory Group
- Aug 31, 2005 Waterford
Click
here for map of Upper Hudson River
What
are PCB's? - Click Here.
Site
Description